Jahra Court Complex

Contact Value  79,650,000.000 KD
Commencement Date 01-Nov-2013
Contractual Completion Date  23-Jun-2015
Client  Amiri Diwan
Project Total Duration  600 Days
Consultant  Pan Arab Consulting Engineers (PACE)
Contractor M.A. Kharafi & Sons Co.

 

The site is located in North West Al Jahra area and surrounded by Marzouk Al Meteb Street on North East side, Debal Al Khozaimi Street on Eastside, Al Akbari Road (Roundabout 1) on South West side near to Abdulla Al Mubarak Mosque.

Project Description:

  1. Court Complex Building: State-of-Art very high quality building having three basement levels, ground floor and sixteen floors above the ground floor. The building comprises Supreme Court, Administration, Criminal and General Prosecution. The building is on 10,000 m2 area plot and having total build up area of approximately at 95,026 m2.
  2. Car Park Building: The combine automated and conventional car park building comprising three basement levels, ground floors and nineteen floor above ground floor. The three basement levels, ground floor and five floors above are for conventional car park facility having 646 car parking spaces. The fourteen floors above fifth floor are for automated car park facility having 2280 car parking space. The total parking facility is for 2926 cars. The building is on 5000 m2 area plot with total built up area of approximately 104869 m2.

 

 Project Photo Gallery